East Washington Ave. Construction Update

July 13, 2007 | Editor
 

Here’s the planned work for the week of July 16 for East Washington Avenue (Second Street to Marquette Street)

Stage 4 - Reconstruction of the inbound lanes from 3rd to 7th Street:

  • Removal of existing pavement and grading
  • Water main construction
  • Sanitary Sewer construction

Stage 2 - Reconstruction of the outbound lanes from Milwaukee Street to Marquette Street:

  • Concrete Paving: median lane paved early next week, intersection work
  • Marquette Street anticipated to be closed on Tuesday 7/17 thru Friday 7/20 for concrete paving
  • Bridge work for the new pedestrian structure, and work beginning on the north side of East Washington Avenue
  • Work by private utility companies

Bus stops will be maintained in the construction zone, See Metro website or project website - “Metro Transit During Construction� for details. There will be no parking on East Washington Avenue in the construction zone. Alternative Routes are I90/94 and the beltline. The field office phone is (608) 242-7305, fax is (608) 242-7317. The website will be updated: http://www.eastwashington.org/