Here’s the planned work for the week of July 30 for East Washington Avenue (Second Street to Marquette Street):

Stage 4 - Reconstruction of the inbound lanes from 3rd to 6th Street:

  • Sanitary sewer and water services
  • Storm Sewer construction
  • Grading
  • Concrete paving anticipated late in the week
  • Work by private utility companies

Stage 2 - Reconstruction of the outbound lanes from Milwaukee Street to Marquette Street:

  • Concrete - sidewalks and driveways
  • Topsoil and sod
  • Asphalt pavement on the side roads
  • Electrical work
  • Bridge work for the new pedestrian structure, and work on the north side of East Washington Avenue

See Metro website or project website for more information - “Metro Transit During Construction� for details. There will be no parking on East Washington Avenue in the construction zone. Alternative Routes are I90/94 and the beltline. The field office phone is (608) 242-7305, fax is (608) 242-7317. The website will be updated: http://www.eastwashington.org/

Tom Riffle
Facilities Operations Manager