East Washington Ave. Construction Update
August 23, 2007 | EditorHere’s the planned work for the week of August 27 for East Washington Avenue (Second Street to Marquette Street)
Stage 5 – Reconstruction of the median from 3rd to 6th Street:
- Topsoil and landscaping work
- Median concrete curb and gutter and median paving
- The median at 4th Street is anticipated to be closed from Tuesday 8/28 to Wednesday 8/29 for concrete paving. Traffic will be restricted to right in and right out access to and from East Washington from 4th Street.
- Electrical work in the median
Stage 4 – Reconstruction of the inbound lanes from 6th Street to Marquette Street:
- Removal of existing roadway and grading
- Water main construction
- Bridge work for the new pedestrian structure
- Demolition of existing roadway bridge
- Work by private utility companies
See Metro website or project website for more information - “Metro Transit During Construction� for details. There will be no parking on East Washington Avenue in the construction zone. Alternative Routes are I90/94 and the beltline. The field office phone is (608) 242-7305, fax is (608) 242-7317. The website will be updated: http://www.eastwashington.org/Tom Riffle