East Washington Ave. Construction Update

August 23, 2007 | Editor
 

Here’s the planned work for the week of August 27 for East Washington Avenue (Second Street to Marquette Street)

Stage 5 – Reconstruction of the median from 3rd to 6th Street:

  • Topsoil and landscaping work
  • Median concrete curb and gutter and median paving
  • The median at 4th Street is anticipated to be closed from Tuesday 8/28 to Wednesday 8/29 for concrete paving. Traffic will be restricted to right in and right out access to and from East Washington from 4th Street.
  • Electrical work in the median

Stage 4 – Reconstruction of the inbound lanes from 6th Street to Marquette Street:

  • Removal of existing roadway and grading
  • Water main construction
  • Bridge work for the new pedestrian structure
  • Demolition of existing roadway bridge
  • Work by private utility companies

See Metro website or project website for more information - “Metro Transit During Construction� for details. There will be no parking on East Washington Avenue in the construction zone. Alternative Routes are I90/94 and the beltline. The field office phone is (608) 242-7305, fax is (608) 242-7317. The website will be updated: http://www.eastwashington.org/Tom Riffle