East Washington Ave. Construction Update
September 13, 2007 | EditorHere’s the planned work for the week of September 17 for East Washington Avenue (Second Street to Marquette Street)
Work in the median from 3rd to 6th Street (possible lane closure from 9 a.m. to 3 p.m.)
- Topsoil and landscaping work
Stage 4 – Reconstruction of the inbound lanes from 6th Street to Marquette Street:
- Water main construction from Johnson to Marquette Street
- Sanitary sewer construction from Dayton to Oak Street
- Storm sewer construction from North Street to Johnson Street
- Grading and base course from North Street to Johnson Street
- Electrical work
- Bridge work for the new pedestrian structure
- Bridge work for the new roadway bridge
- Work by private utility companies
See Metro website or project website for more information - “Metro Transit During Construction� for details. There will be no parking on East Washington Avenue in the construction zone. Alternative Routes are I90/94 and the beltline. The field office phone is (608) 242-7305, fax is (608) 242-7317. The website will be updated: http://www.eastwashington.org/Tom Riffle