East Washington Ave. Construction Update

September 27, 2007 | Editor
 

Here’s the planned work for the remainder of the week:

  • Concrete pavement from Johnson Street to 6th Street
  • North Street remains closed until Saturday for sanitary sewer and storm sewer
  • Crews are continuing installation of sanitary sewer from Johnson to Oak Street
  • The intersection of McCormick and East Washington will be closed at 7:30am on Thursday and be opened later that same day
  • Oak Street will close on Friday and be closed into next week

Here’s the planned work for the week of October 1 for East Washington Avenue (Second Street to Marquette Street):

Work in the median from 3rd to 6th Street (possible lane closure from 9am to 3pm)

  • Installation of new fence

Stage 4 – Reconstruction of the inbound lanes from 6th Street to Marquette Street:

  • North Street will close again at 6am on Monday 10/1 thru Thursday 10/4 for concrete paving of East Washington and North Street
  • Concrete paving the other lanes on East Washington from Johnson Street to 6th Street, and paving of 7th Street, North Street and Pawling Street
  • Sanitary sewer construction from Johnson to Marquette Street
  • Storm sewer construction from Johnson Street to Oak Street
  • Grading and base course from Johnson Street to Oak Street
  • Electrical work
  • Bridge work for the new pedestrian structure
  • Bridge work for the new roadway bridge
  • Water main and sanitary sewer construction from Starkweather Creek to McCormick
  • Work by private utility companies

See Metro website or project website for more information - “Metro Transit During Construction� for details. There will be no parking on East Washington Avenue in the construction zone. Alternative Routes are I90/94 and the beltline. The field office phone is (608) 242-7305, fax is (608) 242-7317. The website will be updated: http://www.eastwashington.org/Tom Riffle
Facilities Operations Manager