East Washington Ave. Construction Update
October 26, 2007 | EditorHere’s the planned work for the week of October 29 for East Washington Avenue (Second Street to Marquette Street):
6th Street to Johnson Street:
- Traffic switch to stage 5 (two inbound lanes of traffic will be switched onto the new concrete pavement from Johnson to 6th Street.
- Median work – concrete curb and gutter, electrical work, topsoil
Johnson Street to McCormick Street (traffic is in stage 4, construction on the inbound lanes):
- Concrete curb and gutter
- Concrete sidewalks and driveways
- Bridge work for the new pedestrian structure
- Bridge work for the new roadway bridge
See Metro website or project website for more information - “Metro Transit During Construction� for details. There will be no parking on East Washington Avenue in the construction zone. Alternative Routes are I90/94 and the beltline. The field office phone is (608) 242-7305, fax is (608) 242-7317. The website will be updated: http://www.eastwashington.org/
Tom Riffle
Facilities Operations Manager