East Washington Ave. Construction Update

November 15, 2007 | Editor
 

Here’s the planned work for the week of November 19 for East Washington Avenue (Second Street to Marquette Street):

  • Electrical work
  • Pavement Marking
  • Bridge work for the new pedestrian structure
  • Construction of bike path along Starkweather Creek

Here’s the planned work for the week of November 26 for East Washington Avenue (Second Street to Marquette Street):

  • Median Landscaping
  • Electrical work
  • Bridge work for the new pedestrian structure
  • Construction of bike path along Starkweather Creek

See Metro website or project website for more information - “Metro Transit During Construction� for details. There will be no parking on East Washington Avenue in the construction zone. Alternative Routes are I90/94 and the beltline. The field office phone is (608) 242-7305, fax is (608) 242-7317. The website will be updated: http://www.eastwashington.org/

Tom Riffle
Facilities Operations Manager