Weekly Road Construction Update

July 15, 2009 | wbessette
 

Here’s the planned construction for the week of July 20. The road work may cause some detours or delays for your drive to work.

East Washington Avenue
–Removal of pavement and grading
–Water main construction
–Sanitary sewer construction
–Storm sewer construction
–Demolition of existing inbound bridge
–Pile driving for new bridge

Highway 30/Aberg Avenue
–Traffic control
–Concrete paving
–Pavement marking

Fair Oaks/Commercial Avenues:
–Westbound HWY 30 on-ramp to Fair Oaks is CLOSED

Bus stops will be maintained in the construction zone. If you have questions about your route call Metro Transit at (608) 204-9000.

Thanks.

Tom Riffle
Facilities Operations Manager
608-243-4020